CB-622 lead follow-up: the three changes no worker could make #136

Merged
ltms merged 1 commits from lead/cb-622-followup into main 2026-08-22 21:59:46 +02:00

1 Commits

Author SHA1 Message Date
Dai Ha 3aea4e1ec6 CB-622 lead follow-up: the three changes no worker could make
CI / contract (pull_request) Successful in 1m10s
CI / build (pull_request) Successful in 1m30s
1. opencode.json — mount key bridged -> fleetd. Unit C could not do this:
   the file is neutralized by the worktree overlay, so every worker sees a
   stub and correctly reported it held no mount key. Tracked as CB-628.

2. e2e/bridge_ask_transcript.md keeps its name. It is a dated record of a
   run on 2026-07-16 that really did call bridge_ask, and its first line
   says so. The harness now writes fleet_ask_transcript.md for new runs;
   its header already says 'Live fleet_ask', so the two now agree.

3. docs/MCP-Contract.md line 20 — the historical banner describes section
   6, and section 6 now says fleet_ask.